Beznau nuclear power plant: Unit 1 back on grid after scheduled outage

22.05.2020 – The Beznau nuclear power plant (KKB) has completed refurbishment work on Unit 1 and reconnected the reactor to the grid today following the approval of the Swiss Federal Nuclear Safety Inspectorate (ENSI). It was possible to complete the work on schedule despite all the corona-related restrictions and additional efforts. 

The focus of refurbishment comprised maintenance work, recurring tests and inspections. In addition, integral system tests were carried out as usual. Of the 121 fuel assemblies, 20 were replaced with new elements and installed in the reactor core.

As usual during a restart, KKB will also conduct various, additional safety tests on Unit 1 and gradually take up full-load operation. The plant will be back to full load in three days.

During refurbishment the approx. 460 employees at KKB were supported by some 400 external specialists from the region, as well as from Switzerland and abroad. KKB implemented strict measures to prevent the spread of the corona-virus and to protect its own and external staff. Entrance checkpoints, strict adherence to hygiene and distancing rules, health check-ups, quarantine in suspected cases, split operation and home office proved to be effective. No corona-virus infections occurred.

At times, visible steam will be emitted from the non-nuclear section of the plant during the restart. This does not pose any danger to human beings or the environment.

All work was supervised by the Federal Nuclear Safety Inspectorate ENSI.

Axpo Holding AG

Corporate Communications

medien@axpo.com

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Ad hoc announcement 19.12.2023

Axpo sells three wind farms in France

Axpo has agreed the sale of three wind farms in France with a combined capacity of 72 MW to an Article 9 fund advised by EB – Sustainable Investment Management GmbH (EB-SIM), it was announced today. The transaction sees Axpo continue to generate strong revenues from its extensive wind farm portfolio and development pipeline. Axpo will continue to provide technical and commercial management services for the portfolio following the sale.

Read more

Renewable energy 15.12.2023

Axpo battery storage in Poland will aid grid stability

Axpo has been active in the development, construction and commercial optimisation of large-scale battery solutions for several years. Following the expansion of these services to the Swedish market, Axpo is launching a dedicated battery business in Poland. The company plans to support stabilisation of the Polish power grid through storage facilities while also participating in the country’s capacity mechanism and trading on short-term markets.

Read more

Solar energy 14.12.2023

Axpo to focus on large-scale solar projects in Italy

Axpo is expanding its solar energy presence in Italy with the development of two new large-scale power plants in the north and south of the country, it was announced today. Leveraging the company’s solar expertise to further exploit its potential in Italy, a strategically important market, is part of the Axpo Group’s continuing commitment to a more sustainable energy supply.

Read more