Beznau nuclear power plant: Unit 2 back on grid after scheduled outage

The Beznau nuclear power plant (KKB) has completed refurbishment work on Unit 2 and reconnected it to the grid today following the approval of the Swiss Federal Nuclear Safety Inspectorate (ENSI).

The focus of refurbishment comprised maintenance work, recurring tests and inspections as well as the commissioning of new systems. In addition, integral system tests were carried out as usual. Of the 121 fuel assemblies, 20 were replaced with new elements and installed in the reactor core.

During the restart, KKB will conduct various, additional safety tests on Unit 2 and gradually take up full-load operation. Unit 2 will be back to full load in about two to three days.

At times, steam will be emitted from the non-nuclear section of plant during the restart. This does not pose any danger to human beings or the environment.

Axpo Holding AG

Corporate Communications

medien@axpo.com

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Renewable energy 26.06.2024

Axpo gives investment green light for Vörå wind farm

Read more

Hydropower 25.06.2024

Gigerwald dam facility: Renovation work resumed

Read more

International business 28.08.2024

Axpo offtakes 1.5 TWh of green energy annually from RWE in Poland

Read more